Hi guys.
I have a production order PO1. PO1 has one operation with work center WC1 (WC1 has one activity defined-MACHINE MC1).
PO1 is already released.No confirmation has been carried yet.
Now I have added one more activity in WC1, say LABOUR LC1.
If I confirm the operation with work center WC1, cost is not getting booked for the new activity LC1 but the hours are booked.
But if I remove and add the same work center against the same operation or add new operation with same work center, cost is getting booked for PO1.
I have nearly 500 production orders already released with work center WC1.
I don't want to remove and add the same work center in the production orders to book the labour activity LC1 costs.
How to solve this issue?
Thanks in advance.